Understanding and Implementing Effective Erosion Control

Erosion control and sediment control are two different jobs, and a site that confuses them fails inspections in both directions. Erosion controls keep soil where it is: cover, mulch, seed, blankets, and the dikes and swales that keep runoff from crossing bare ground. Sediment controls catch the soil that moves anyway: fences, berms, inlet barriers, traps and basins. The Environmental Protection Agency organizes its national menu of construction practices on exactly that split, with runoff control and good housekeeping as the third and fourth groups4, and the Texas construction general permit expects a Stormwater Pollution Prevention Plan to draw from each group for the site in front of it rather than copy the last one1.

This is the catalog: what each control is for, where it belongs, how it is specified in Texas, and what fails first. It is written for North Texas ground, which changes some of the answers. Clay runs off rather than soaking in, it blinds fabric, and it stays suspended in water long after sand has settled. The regional iSWM construction manual rates a sediment basin's effectiveness at 0.90 on sand and 0.50 on clay3, which is the most useful number on this page: on Blackland sites, keeping the soil in place is worth about twice what catching it is.

Erosion controls: keeping the soil where it is

Mulch and hydraulic mulch

Mulching stabilizes exposed or freshly seeded soil with straw, hay, wood chips, wood fiber or gravel, and it does its best work combined with seeding, because it holds seed, fertilizer and moisture in place while the stand comes up10. On steep slopes and near water, loose mulch needs netting, anchoring or a tackifier, or a hydraulically applied mulch takes its place10. On Texas state work, temporary and permanent seeding sit in the list of control measures under Item 506, and every erosion and sediment control device has to come from the Erosion Control Approved Products List15.

Seeding

Seeding is the erosion control that ends the job, because the permit's definition of final stabilization is a uniform perennial vegetative cover with a density of at least 70 percent of the native background cover on every unpaved area not covered by a permanent structure1. EPA describes permanent seeding as the right choice for roughly graded areas that will not be regraded for at least a year11. TxDOT's Item 164 buys seed by pure live seed, purity times germination, under the Texas Seed Law, sets its rates for drill seeding and raises them 25 percent for any other method, and publishes a permanent rural mix by district and by soil. For the Fort Worth district on clay soils the mix is hooded windmillgrass, white tridens, sideoats grama, little bluestem, buffalograss, silver bluestem, green sprangletop, sand dropseed and Canada wildrye16. That table is the closest thing to a regional answer to "what do we plant" that exists in a public specification.

Erosion control blankets

Blankets hold seed and soil in place until vegetation establishes, and iSWM names slopes, embankments and small swales as where they earn their keep3. TxDOT calls them soil retention blankets and specifies them in four dimensions: moderate slopes at 3:1 or flatter against steep slopes steeper than 3:1, clay against sandy soil, rolled against sprayed product, and a duration class in which a rolled short-term blanket lasts up to 12 months and a long-term one 12 to 35 months17. Channel blankets are specified by the shear stress they must survive, 2, 4, 6 or 8 pounds per square foot17. The blanket goes down within 24 hours of seeding, over ground mowed to 4 inches and cleared of the rocks and clods that would hold it off the soil17. EPA's fact sheet covers the materials: woven and non-woven geotextiles, and matting and netting of jute, coir and wood fiber that hold mulch and seed while plants take12.

Check dams, dikes and slope drains

Three controls manage water that is already running rather than the ground it runs over. A check dam is a small temporary structure in a swale or ditch that reduces flow velocity; EPA's guidance is to space them so the base of the upstream dam sits at the elevation of the top of the downstream dam, to key the material at least 6 inches into the sides and bottom of the channel, and never to rely on them for sediment trapping alone8. iSWM's erosion section adds the diversion dike, which keeps clean runoff off disturbed ground, and the interceptor swale, which cuts a long slope into shorter ones3. A temporary pipe slope drain carries concentrated flow down a fill slope in a pipe instead of letting it cut a gully; TxDOT specifies the pipe, fittings and flared entrance under Item 50615.

Sediment controls: catching what moves

Silt fence

Silt fence is a temporary barrier of porous fabric on posts; the fabric impounds sediment-laden runoff so the soil settles behind it5. It works only on sheet flow. iSWM places it on the downslope perimeter of disturbed areas and warns that where flows concentrate, at an inside corner or across a gully, the fence has to be backed by a rock or sandbag berm3. The same manual carries the caution that matters most here: silt fence is most effective on coarse to silty soils and should be used with caution where the soil is predominantly clay, because it clogs and the fine fraction passes through or over it3. EPA's sheet is blunter: poor placement can make the fence a complete waste, and the site's contours decide where it goes5. TxDOT's temporary sediment control fence is net-reinforced: fabric to DMS-6230, posts at least 48 inches long, and galvanized welded wire of at least 12.5 gauge with openings no larger than 2 by 4 inches behind the fabric15. DMS-6230 defines that fabric as a woven geotextile whose primary use is control of sediment in surface runoff, sampled and tested to the department's methods and carried on a material producer list19.

Rock filter dams and sandbag berms

Where fabric cannot stand, rock does. Item 506 specifies four types of rock filter dam, built of 3 to 6 inch aggregate for Types 1, 2 and 4 and 4 to 8 inch aggregate for Type 3, with galvanized wire mesh holding Types 2 and 3 together and a double-twisted hexagonal mesh basket for Type 415. Sandbags for berms are woven polypropylene, polyethylene or polyamide filled with coarse sand, 24 to 30 inches long and 6 to 8 inches thick15. Both belong at the mouths of swales, below stockpiles, and at the corners of a fence line where the flow concentrates.

Inlet protection

Inlet protection keeps soil out of the storm drain, and EPA calls it often the last opportunity to treat runoff before it leaves the site6. Internal inserts catch only larger sediment; external barriers of stone, gravel or fabric impound water around the inlet so the sediment settles first6. iSWM is clear about its rank: it is a secondary barrier, a backup behind newly applied erosion controls, and may serve as a primary control only when every other primary control is infeasible3. The manual's schematics cover the inlets North Texas cities actually build, weir curb inlets, on-grade curb inlets and area inlets, in block-and-gravel, filter fabric and organic filter tube versions3.

Stabilized construction exit

The exit is the control the neighbors notice. A pad of gravel over filter cloth where traffic leaves the site knocks mud off the wheels, and the cloth separates the stone from the soil beneath so the pad does not sink or rut7. iSWM adds a second purpose: one exit, or two on a large site, channels traffic so vehicles stop driving over the other controls3. TxDOT's rock construction exit uses 4 to 8 inch aggregate for Type 1 and 2 to 4 inch for Type 3 over a foundation course, with a timber exit of railroad ties as the long-term alternative15. A wash station with its water routed to a sediment trap is the upgrade when a pad is not enough7.

Sediment traps and basins

A basin lets water impound in an excavated or natural depression so sediment settles, dewatered through a riser and outlet on an earthen embankment or through the voids of a rock dam; rock dams suit drainage areas under 50 acres9. The permit requires a basin or similar impoundment, where feasible, at any common drainage location serving ten or more acres disturbed at one time, sized to hold the runoff of a 2-year, 24-hour storm from each disturbed acre, or 3,600 cubic feet of storage per acre drained where rainfall data is not available or the calculation cannot be performed1. Below ten acres, traps and basins are optional and silt fence, vegetative buffer strips or an equivalent are the minimum on every downslope boundary1. iSWM sizes basins, details a surface skimmer and an overflow riser, and rates their efficiency by soil: 0.90 on sand and sandy loam, 0.75 on silt loam and silty clay loam, 0.50 on clay loam and clay3. On clay, drawdown time is the design. The water has to sit long enough for particles that do not want to settle.

Dust

Dust is erosion by wind, and on a summer clay site it is the control that gets the phone call. EPA treats it as both a water and an air problem, since airborne soil lands in waterbodies and raises particulate matter, PM10 and PM2.5, in the surrounding area, and its first illustration of a measure is a truck with a spray system watering the site13. Item 506 lists vertical tracking, running equipment up and down a slope so its treads leave horizontal grooves, among its control measures15.

The catalog in one table

Construction erosion and sediment controls, what each is for, and how it is specified in Texas
ControlJobWhere it goesSpecified toWhat fails first
Mulch and hydromulchErosionFresh seed, open slopesItem 506, Approved Products List15Blown or washed off without netting or a tackifier10
SeedingErosion, final stabilizationEvery unpaved areaItem 164, pure live seed rates by district16Cover short of 70 percent of native background1
Erosion control blanketErosionSlopes, embankments, small swalesItem 169, DMS-637017Held off the soil by clods, not anchored17
Check damRunoffSwales and ditchesEPA spacing rule8Scour around the ends, silt to the crest8
Diversion dike, interceptor swaleRunoffAbove disturbed groundiSWM3A breach at the low point
Silt fenceSedimentDownslope perimeter, sheet flow onlyItem 506, DMS-62301519Undercut, overtopped, blinded by clay3
Rock filter dam, sandbag bermSedimentConcentrated flow, swale mouthsItem 506 aggregate by type15Silt to the crest, displaced rock
Inlet protectionSediment, secondaryEvery inlet downstream of disturbanceiSWM schematics3Bypassed at the curb, clogged fabric6
Stabilized exitSedimentThe one or two places trucks leaveItem 506 rock sizes15Track-out on the street, pad sunk in mud7
Sediment basinSedimentCommon drainage point, ten acres or moreCGP 3,600 cubic feet per acre; iSWM13Short drawdown on clay, riser clogged9
Dust controlErosion by windHaul roads, open padsEPA; Item 5061315A visible plume leaving the site

Specified, not improvised

Every control on this page has a public specification behind it, and the specification is what turns a good intention into a pay item an inspector can accept. On Texas state work the products come off the Erosion Control Approved Products List, which TxDOT builds from field testing at the Texas Transportation Institute's Sediment and Erosion Control Laboratory and which covers rolled and spray-on erosion control, sediment retention devices and revegetation products18. Item 506 describes its scope as installing, maintaining and removing the controls, requires installation and maintenance to the manufacturer's or designer's specifications, and ties the whole item to compliance with the construction general permit15. Private and municipal work in the metroplex more often references the iSWM manual, whose schematics carry the same level of detail for the region's own inlet and channel types3.

The inspection and maintenance clock

A control that is not maintained is a violation with a fence around it. The permit requires inspection of the site at least once every 14 calendar days and within 24 hours of the end of a storm of 0.5 inches or greater, or on an alternative schedule of once every 7 calendar days regardless of rain, and the schedule may change at most once a calendar month1. EPA sorts inspections into three kinds, routine, before a rain event and after one, and its advice for the day before a forecast storm is to walk the site and fix what is damaged before the water arrives14. What the walk finds is specific to each control: sediment against a fence, a check dam silted to the crest, an inlet barrier bypassed at the curb, a pad that has disappeared into the mud, a basin that has lost its storage. The maintenance is inside the pay item on state work, and inside the scope on everything else15.

Stabilization is how it ends

The catalog closes with the clock that matters most. Where earth-disturbing activity has temporarily or permanently ceased, the permit requires stabilization to begin immediately, meaning as soon as practicable and no later than the end of the next work day, and to be completed within 14 calendar days of starting, with exceptions for frozen ground and drought1. When final stabilization is reached on everything the operator is responsible for, a Notice of Termination goes to TCEQ within 30 days, with a copy to the operator of any municipal separate storm sewer system receiving the discharge1. The permit in force is the renewal TCEQ issued with an effective date of March 5, 20232.

IRONWILL Earthworks installs, maintains and removes these controls as part of the grading scope rather than as a trade that arrives afterward. The perimeter goes in before the first cut, the exit is built where the trucks actually leave, the basin is dug with the mass grading, and the inspection log is kept by the people running the site. On Blackland clay we plan for the numbers above: fabric that blinds, water that stays muddy, and a basin that needs time more than it needs size.

Sources

Every number and every rule on this page is cited here. Reviewed September 17, 2026.

  1. Construction General Permit, TPDES General Permit No. TXR150000Texas Commission on Environmental Quality, 2023Inspection every 14 days and within 24 hours of a 0.5 inch storm or every 7 days; stabilization begun by the next work day and completed within 14 days; final stabilization at 70 percent cover; basins for ten or more acres at a common drainage location, 2-year 24-hour storm or 3,600 cubic feet per acre; Notice of Termination within 30 days.
  2. Stormwater General Permit for Construction ActivitiesTexas Commission on Environmental QualityThe renewed permit's effective date of March 5, 2023, and the SWP3 requirement before construction begins.
  3. iSWM Technical Manual: Construction ControlsNorth Central Texas Council of Governments, 2019The regional catalog: silt fence use and its caution on clay soils, inlet protection as a secondary control, stabilized exits, blankets, dikes and swales, sediment basin design, and Table 3.3, basin effectiveness by soil type.
  4. National Menu of Best Management Practices (BMPs) for Stormwater: ConstructionU.S. Environmental Protection AgencyThe four groups of construction practices: erosion control, runoff control, sediment control, good housekeeping.
  5. Stormwater Best Management Practice: Silt FencesU.S. Environmental Protection Agency, 2021What a silt fence is, how it works, and why placement decides whether it works at all.
  6. Stormwater Best Management Practice: Storm Drain Inlet ProtectionU.S. Environmental Protection Agency, 2021Internal and external inlet controls, and inlet protection as the last treatment before discharge.
  7. Stormwater Best Management Practice: Construction Track-Out ControlsU.S. Environmental Protection Agency, 2021The gravel pad over filter cloth, and wash stations draining to a sediment trap.
  8. Stormwater Best Management Practice: Check DamsU.S. Environmental Protection Agency, 2021Spacing, keying 6 inches into the channel, and the rule against using check dams for sediment trapping alone.
  9. Stormwater Best Management Practice: Sediment Basins and Rock DamsU.S. Environmental Protection Agency, 2021Basin dewatering through a riser, and rock dams for drainage areas under 50 acres.
  10. Stormwater Best Management Practice: MulchingU.S. Environmental Protection Agency, 2021Mulch materials, mulch with seeding, and netting, tackifiers and hydromulch on steep slopes.
  11. Stormwater Best Management Practice: Permanent SeedingU.S. Environmental Protection Agency, 2021Permanent seeding for areas that will not be regraded for at least a year.
  12. Stormwater Best Management Practice: Geotextiles, Matting and NettingU.S. Environmental Protection Agency, 2021Woven and non-woven geotextiles, and jute, coir and wood fiber matting and netting.
  13. Stormwater Best Management Practice: Dust ControlU.S. Environmental Protection Agency, 2021Dust as a water and an air problem, PM10 and PM2.5, and watering as the basic measure.
  14. Stormwater Best Management Practice: Erosion and Sediment Control Inspection and MaintenanceU.S. Environmental Protection Agency, 2021Routine inspections, inspections before rain and inspections after rain.
  15. Item 506, Temporary Erosion, Sedimentation, and Environmental Controls, 2024 Standard SpecificationsTexas Department of Transportation, 2024The list of control measures, rock filter dam and construction exit aggregate sizes, sandbag dimensions, the net-reinforced sediment control fence, and the Approved Products List requirement.
  16. Item 164, Seeding for Erosion Control, 2024 Standard SpecificationsTexas Department of Transportation, 2024Pure live seed, drill rates plus 25 percent for other methods, and the permanent rural seeding mix by district and soil, including the Fort Worth district on clay.
  17. Item 169, Soil Retention Blankets, 2024 Standard SpecificationsTexas Department of Transportation, 2024Slope, soil, application and duration categories, channel shear stress classes, and placement within 24 hours of seeding.
  18. Erosion control: products and vendorsTexas Department of TransportationThe Erosion Control Approved Products List, tested at the Texas Transportation Institute's Sediment and Erosion Control Laboratory, covering rolled and spray-on erosion control, sediment retention devices and revegetation products.
  19. DMS-6230, Temporary Sediment Control Fence FabricTexas Department of Transportation, Construction Division, 2010The definition of sediment control fence fabric as a woven geotextile, and the material producer list it is carried on.